Construction Plans: June 18 through August 11, 2024

Second:  We will be having a ramp installed in the front of building running from the bus loop to the front door (door 1).  The doors will be modified to have the handicap capability installed and the contractors will be removing the handicap capability from door 7.

Third:  We will have four new handicap parking spaces put in.  They will be installed on the front lawn close to the entrance door to the library (door 2).

With all of this going on, the main parking lot and a large portion of the bus loop will not be available, nor will the main entrance (door 1) or the kiss and ride doors (door 7 and 8).   

Please review this aerial photo of Neabsco with the unavailable areas marked out with an X.